×

Special Offer! Sale of the Month | Extra 20% OFF - Ends In Coupon code: TEL20

Free Practice Test Prep CCE-CCC Exam Questions 2025

Stay ahead with 100% Free Certified Cost Consultant / Cost Engineer (AACE International) CCE-CCC Dumps Practice Questions

Page:    1 / 24      
Total 118 Questions | Updated On: Apr 22, 2025
Add To Cart
Question 1

A major theme park is expanding the existing facility over a five-year period. The design phase will be
completed one year after the contract is awarded. Major engineering drawings will be finalized two years after
the design contract is awarded and construction will begin three years after the award of the design contract.
New, unique ride technology will be used and an estimate will need to be developed to identify these costs that
have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to
have reached the ______________ stage of Maslow's hierarchy of needs.


Answer: C
Question 2

A major theme park is expanding the existing facility over a five-year period. The design phase will be
completed one year after the contract is awarded. Major engineering drawings will be finalized two years after
the design contract is awarded and construction will begin three years after the award of the design contract.
New, unique ride technology will be used and an estimate will need to be developed to identify these costs that
have no historical data.
A cyclical process model was chosen as the basis for total cost management (TCM) because:


Answer: C
Page:    1 / 24      
Total 118 Questions | Updated On: Apr 22, 2025
Add To Cart

© Copyrights TheExamsLab 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.