Question 1


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)


Answer: D
Question 2

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow’s hierarchy of needs? 


Answer: A
Question 3

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow’s hierarchy of needs? 


Answer: A
Question 4

refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio. 


Answer: D
Question 5

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client. A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%. How does the project stand?


Answer: C
Page:    1 / 39      
Total 191 Questions | Updated On: Apr 21, 2025
Add To Cart

© Copyrights TheExamsLab 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.