Which aspect in the test estimate is the main risk in this project? 1 credit
Which of the following can demotivate a tester?
You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks
and determining the likelihood and impact of those risks. You have been testing for three months and have
been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect
to be able to complete all the items on the high-risk mitigation list, never mind any from the medium or low-risk
lists.
What is the most effective action you should take?