Question 1

Your company has notified the stakeholders that they will be delivering the first release of a new product
within ten Sprints. On the seventh Sprint, the Scrum Team discovers that they will not be able to include all of
the expected features within the first release. The Product Owner believes if they remove some items from the
Definition of Done they will be able to accelerate the development process. The Development Team objects to
this idea as it will lead to technical debt.
As a Scrum Master, what would be the best two ways to explain to the Product Owner the impact of technical
debt? (Choose two.)


Answer: B,C
Question 2

Which of the following is true about the Product Owner role? 


Answer: B
Question 3

Which of the following are time-boxed events in Scrum? 


Answer: A
Question 4

Which role is responsible for determining when it is most appropriate to update the Sprint Backlog? 


Answer: B
Question 5

Which three statements best describe the purpose of having a Definition of Done? (Choose three.) 


Answer: A,B,C
Page:    1 / 45      
Total 221 Questions | Updated On: Sep 03, 2026
Add To Cart

© Copyrights TheExamsLab 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.